Event Updates
The General Contractor KBR and their electricians “Tron Electric” are in the process of installing a new electrical panel in ERP Building #7.
The new electrical panel will be substantially completed by this coming Friday 18 April 2014.
The New panel will be activated by ERP Office of Real Estate Services in coordination with Center Point Energy Monday morning 21 April 2014.
The permanent new electrical service should be restored to Buildings #7 and #6 at the latest by the afternoon of Monday 21 April 2014.
In the interim will confirm with the selected building occupants (C-Voltaics, In particular) in building #7 and #6 if they are in need of any temporary electrical power to support their ongoing operational needs thru the end of this week and the coming Monday morning of 21 April 2014. If these users do need temporary electrical service needs portable electric generators will be proved by KBR for their use as required.