As faculty, staff and students return to the University of
Houston to begin the new semester, they’ll probably notice
that spring campus renovations are well under way.
Those working in the Ezekiel Cullen Building have no doubt
observed activity as a new mechanical system is being installed
in the building. Dave Irvin, associate vice president for facilities
and plant operations, said the current work being performed
in the building is the first phase of a more extensive project.
“E. Cullen is our most energy inefficient building, and
the existing mechanical system doesn’t provide much in
the way of occupants’ comfort,” Irvin said. “We
have to put in new duct work and new mechanical systems. Since
ceilings will be ripped out, we plan to upgrade and remodel
E. Cullen’s corridors.”
Irvin said the remodeled corridors would be similar to the
hall renovations that took place in McElhinney and Farish halls
and the Roy Cullen Building. He added that E. Cullen’s
restrooms also would be renovated to be in full compliance with
the Americans with Disabilities Act. He estimated that the mechanical
system installation would be completed prior to the start of
the semester. The corridor and restroom renovations would take
place mainly during nonbusiness hours, so E. Cullen occupants
would not be inconvenienced. These projects should be finished
by June 1.
Another extensive project is occurring outside of E. Cullen
on the grassy mound located on the building’s east side.
Irvin said that this is a city of Houston project in which large
underground valves that control the main water lines through
the campus are being replaced and moved to E. Cullen’s
south side. This project should improve water conservation and
reliability. Irvin anticipates that this project should be completed
by
Feb. 1.
“We’re in favor of moving these valves because
the campus master plan recommends re-landscaping the east side
of E. Cullen,” Irvin said. “This project ties into
another one that we’ve been planning, which are sidewalk
repairs on the south side of E. Cullen.”
In addition to these projects, work continues on the Lamar
Fleming Jr. and Fred Heyne buildings. The exterior waterproofing
on both of these began to fail following heavy rains during
the fall semester. Following a massive excavation around both
buildings, the exterior drains will be replaced with new materials
and a synthetic waterproofing material will be applied to all
of the two building’s exterior walls. Accessibility will
be maintained throughout the project, and the most disruptive
work will occur during nonbusiness hours. Work on these facilities
began during the winter break and is expected to continue through
mid-spring.
Mike Emery
memery@central.uh.edu