SR1 Life Safety Project Updates:
- The basement mechanical room air handler is being monitored daily while awaiting parts to fix current issues
- The 5th floor mechanical room air handler is being monitored daily while awaiting parts to fix current issues
- HVAC repairs and replacement are ongoing throughout the building and are being scheduled through NSM for access to certain areas
- The removal of one of the old building chilled water risers occurred this past weekend
- Basement mechanical room work is ongoing
- Testing and Inspections of the Entire Life Safety System by the UH Fire Marshal should occur towards the end of July or early August
- The general refresh being done to the building restrooms is currently in the bidding process
- The stairwell refresh is ongoing – final design to be determined towards the end of July or early August
- Door repair rooms 127, 136, 312 and 323 - COMPLETE
- Loading dock door will be retrofitted with new continuous locking hardware pending funding – zone managers will be securing doors nightly until retrofit is complete
Please report any facility issues to your Building Coordinators (Fred McGhee, 713-743-8631, or Mike Mahanay, 713-743-3718) and the UH Facilities Service Center at 713-743-4948
Thank you in advance to our building occupants and stakeholders for your continued patience during this on-going process. For more information, see SR1 Life Safety Updates project.